Case Study
Davit Arm Fabrication
Introduction
Our client needed to install scaffolding to completely replace crane rails above 5 bunkers at their energy from waste facility.
Challenge
This scaffolding could only be installed during a 3 day working window, and would have required a costly and time consuming hanging scaffold, this was not feasible so an alternative solution was urgently required.
Solution
Working with the client, a design was agreed to provide a permanent installation of a support system that could be erected before the shutdown and hinged into position only when required. 110 manufactured in total using coded MIG, all passing NDT 100%. Continuous deliveries using IME transport for a seamless install.
Result
Successful project and happy customer, avoiding the need for expensive scaffold.